Problem 1 · Cost types and breakdowns
Select all that apply.
A precast concrete plant is classifying its costs. Which of the following are variable costs that change in proportion to the number of panels produced? Select all that apply.
- A.Cement and aggregate used in each panel
- B.The plant manager's annual salary
- C.Annual property insurance on the plant
- D.Steam and electricity used to cure each casting
- E.Straight-line depreciation on the casting beds
- F.Piece-rate wages paid per panel finished
Show the answer and solution
Answer: A: Cement and aggregate used in each panel; D: Steam and electricity used to cure each casting; F: Piece-rate wages paid per panel finished
Variable costs rise and fall with production volume: materials, curing energy per casting, and piece-rate labor. Fixed costs such as salaries, insurance, and time-based depreciation are incurred regardless of how many panels are made.
Cost types and breakdowns · Reference Handbook: Engineering Economics